6-K ·Filed Jul 15, 2026

AYA

Aya Gold & Silver Inc.
NEUTRAL
Impact 4/10
Horizonmonths Processed4mo ago SEC0001628280-26-048259
Notable filing: 6-K
Actionable Insight • Neutral

This is a routine project update with no catalysts expected until the updated PEA (H2-2026) or the feasibility study completion (H2-2027). Monitor for the Q2-2026 earnings release on August 13, 2026, for operational and financial metrics from the producing Zgounder mine. The Boumadine tender outcomes and metallurgical results near-term are unlikely to move shares independently.

DirectionNeutral
Confidencehigh
Horizonmonths

How the stock moved after the report

⚠ Clustered NEUTRAL VIEWSTOCK ABOVE ENTRY AT T+60
Entry
$19.75
T+0 close · Jul 15, 2026 · via day close
Latest settled
+33.27%
T+60 · $26.32
Vs SPY
+30.73%
α at T+60
Horizons
All settled
through T+60
  1. T+0 · Jul 15 $19.75entry
  2. T+1 · 4mo ago −5.06%α −4.52% · $18.75
  3. T+5 · 4mo ago +5.82%α +6.80% · $20.90
  4. T+20 · 3mo ago +41.97%α +39.63% · $28.04
  5. T+60 · 6w ago +33.27%α +30.73% · $26.32
Loading chart...

How similar events traded

How similar events traded

See how far stocks moved after events like this one.

Subscribe for Full Access

Executive Summary

Aya Gold & Silver filed a 6-K providing a progress update on the Boumadine Feasibility Study (target completion H2-2027) and updated PEA (target release H2-2026). The update covers infill drilling (102,111m YTD), contractor tender processes, water/power infrastructure studies, and metallurgical testwork. This is a routine operational progress report with no new financial data, production results, or material changes to project economics.

Key Facts

  • 102,111 metres of infill drilling completed YTD as part of 360,000m campaign; 180,000m targeted for 2026
  • Feasibility study on track for completion by H2-2027
  • Updated PEA on track for release in H2-2026 with revised resource model, mine plan, and metal prices
  • Competitive tender for open pit mining contract expected to be completed in H1-2027; processing plant shortlist by year-end
  • Metallurgical testwork program led by SGS Canada in final phase; processing team satisfied with results
  • Q2-2026 financial results to be released August 13, 2026, with conference call on August 14
  • Pre-qualified mining contractors identified; early works including project access road planned to start by year-end

Financial Impact

No financial figures reported in this filing.

Risk Factors

  • Delay risk on Boumadine feasibility study or updated PEA timelines
  • Project execution and financing risk for a large-scale polymetallic development
  • Permitting, infrastructure, and contractor availability risks in Morocco

Market Snapshot

Exchange
Nasdaq
Analyst Consensus
93% bullish (14 analysts)

Documents Analyzed

This report is based on 5 SEC documents filed with EDGAR.

DocumentAccession Number
6-K Filing (Primary)0001628280-26-048259
Document: a6k2026july15pressrelease.htm0001628280-26-048259
Document: 0001628280-26-048259-index-headers.html0001628280-26-048259
Document: 0001628280-26-048259-index.html0001628280-26-048259
Document: 0001628280-26-048259.txt0001628280-26-048259

US Market Status

Market Closed · Opens in 7h 37m

Subscribe to SecBot

Get Real-Time SEC Filing Intelligence

Comprehensive SEC filing analysis delivered the moment filings hit EDGAR. Sentiment scoring, impact analysis, and actionable insights for every material event.

Create a free account Live analysis, Telegram alerts, watchlists and the MCP server for subscribers
Report published Jul 15, 2026