WULF · TeraWulf acquired a 1+ GW hyperscale development site (Muskie Data…

TERAWULF INC. · 8-K filed May 26, 2026 at 08:06 ET

At the news

NEUTRALIMPACT 5/10

8-K filed May 26, 2026 at 08:06 ET

TeraWulf acquired a 1+ GW hyperscale development site (Muskie Data Campus) in Eastern Kentucky from Industrial Equity Partners, closed May 22, 2026. The ~285-acre site can support up to 1 GW of AI/HPC capacity, with initial 500 MW delivery expected H2 2028 and another 500 MW in H2 2030. No purchase price or acquisition cost was disclosed. The filing expands TeraWulf's multi-campus development pipeline and aligns with its stated strategy of securing power-advantaged sites, but adds no near-term revenue and requires significant future capital investment.

  • Acquired ~285-acre hyperscale development site in Eastern Kentucky (Muskie Data Campus) from Industrial Equity Partners
  • Expected to support up to 1 GW of data center capacity, 500 MW initial delivery H2 2028, additional 500 MW H2 2030
  • Site includes option for adjacent acres; Kentucky Power building 345 kV substation connected to 765 kV network
  • Transmission and energy service agreements executed concurrently; no third-party consents or regulatory approvals required