At the news
? MIXEDIMPACT 6/10 6-K filed Mar 31, 2026 at 08:24 ET
Skeena Resources provided a project update confirming its Eskay Creek Gold-Silver Project is 49% complete as of February 28, 2026, with initial production still on track for Q2 2027. The company revised its construction cost estimate to $659 million, an increase of $99 million from the 2023 DFS, due to inflation, stricter environmental standards, and design enhancements, partially offset by $94 million in leasing arrangements.
- Eskay Creek Project is 49% complete as of February 28, 2026
- Initial production remains on schedule for Q2 2027, commercial production expected in Q3 2027
- Updated construction cost estimate is $659 million, up $99 million from the 2023 DFS estimate of $560 million
- $94 million in leasing arrangements for water treatment, electrical infrastructure, and camp facilities has reduced upfront capital requirements
Before · The news · First close · A day later · A week later
Replay the market's reaction
Step through every 5 minutes around the news, then see how it compares with similar events.
Subscribe for Full Access