? MIXEDIMPACT 6/10 PRESS-RELEASE filed Mar 31, 2026 at 08:20 ET
Skeena Resources updated the construction cost estimate for its Eskay Creek Gold-Silver Project to $659 million, a $99 million increase from the 2023 DFS estimate, citing inflation, enhanced water treatment requirements, and design improvements. Despite the cost hike, the project remains on schedule for initial production in Q2 2027 and commercial production in Q3 2027, with 49% construction completion as of February 28, 2026.
- Updated construction cost estimate for Eskay Creek Project is $659 million, up $99 million from the 2023 DFS estimate of $560 million.
- Cost increase driven by inflation, stricter water discharge standards, Impact Benefit Agreement commitments, design enhancements, and a six-month schedule extension.
- Leasing arrangements for key infrastructure have reduced upfront construction costs by $94 million.
- Project is 49% complete as of February 28, 2026, with 66% of total costs now contractually committed.
Before · The news · First close · A day later · A week later
Replay the market's reaction
Step through every 5 minutes around the news, then see how it compares with similar events.
Subscribe for Full Access