? BULLISHIMPACT 6/10 8-K filed Nov 12, 2026 at 07:00 ET
Fermi announced agreements with an investment-grade hyperscaler for 600 MW of power capacity at Project Matador, including a $200M prepayment and a $15M early construction agreement, while also terminating its TensorWave lease. The company reported a Q3 2026 net loss of $141.6M ($0.22 per share), remains pre-revenue, and had $315.5M in cash and restricted cash with $958.4M in net debt. The hyperscaler commitment is a major milestone that validates Fermi's business model and provides non-dilutive capital, but the company remains pre-revenue with significant cash burn.
- Signed agreements with an investment-grade hyperscaler for 600 MW of power capacity at Project Matador, including a $200M prepayment and a $15M early construction agreement
- Finalizing a $90M structural steel and building materials purchase agreement with the same customer
- Terminated the TensorWave Data Center Lease and Services Agreement signed in August 2026
- Q3 2026 net loss of $141.6M ($0.22 per basic and diluted share), compared to a net loss of $346.8M ($0.84 per share) in Q3 2025
Before · The news · First close · A day later · A week later
Replay the market's reaction
Step through every 5 minutes around the news, then see how it compares with similar events.
Subscribe for Full Access