DUK · The Ohio Supreme Court affirmed a Public Utilities Commission order…

Duke Energy CORP · COURT-RULING filed Jun 4, 2026 at 20:00 ET

At the news

BULLISHIMPACT 5/10

COURT-RULING filed Jun 4, 2026 at 20:00 ET

The Ohio Supreme Court affirmed a Public Utilities Commission order allowing Duke Energy Ohio to recover ~$29M in costs related to retiring its propane caverns through customer rates over 10 years. The ruling upholds the commission's classification of the deferred net book value (~$17M) as an operating expense under R.C. 4909.15(A)(4) rather than a capital investment subject to the 'used and useful' test, removing a regulatory challenge that could have blocked recovery of ~$2.9M/year in rates.

  • Ohio Supreme Court affirmed PUCO order allowing Duke Energy Ohio to recover ~$29M in propane-cavern retirement costs via customer rates over 10 years (~$2.9M/year).
  • The court rejected the Office of the Ohio Consumers' Counsel's argument that the net book value (~$17M) should be subject to the 'used and useful' standard under R.C. 4909.15(A)(1).
  • The court held the deferred amount was properly classified as a cost of rendering public-utility service under R.C. 4909.15(A)(4), citing the caverns' 60+ years of service and the routine nature of retiring aging utility assets.
  • The ruling is final from the Ohio Supreme Court; no further appeal is available within the state system.