Denison Mines announced the transition from site preparation to full-scale construction at its Phoenix ISR uranium mine, including initiation of the freeze wall installation. This milestone follows regulatory approvals (Saskatchewan EA in July 2025, CNSC construction license in February 2026) and marks a key step toward becoming Canada's first new large-scale uranium mine since Cigar Lake. The filing contains no financial data, revenue, or earnings, it is a pure operational update on a pre-revenue development-stage project.

  • Denison announced commencement of full-scale construction at the Phoenix ISR uranium mine, including initiation of the perimeter freeze wall installation.
  • Site preparation activities completed since March 2026 include substantial site clearing, civil works, and establishment of temporary construction camp facilities (capacity ~400 people).
  • Over 20% of overall site civil work estimated complete; near 100% completion of civil subgrade work for process plant and wellfield areas.
  • Concrete pours for substation and main process plant foundations expected to commence in August 2026.