At the news
? BULLISHIMPACT 7/10 COURT-RULING filed Jun 2, 2026 at 20:00 ET
The Fourth Circuit vacated a preliminary injunction that had barred Chemours from discharging HFPO-DA (GenX) above its Clean Water Act permit limits at its Washington Works plant. The appellate court found the district court committed legal errors in its irreparable harm analysis, including improperly presuming irreparable harm from a CWA violation and relying on expert testimony that showed only an increased risk of harm, not a likelihood. The ruling removes the immediate threat of a production curtailment or shutdown order, which is a material positive for Chemours' operations.
- Fourth Circuit vacated preliminary injunction that had restricted Chemours' HFPO-DA discharges at Washington Works.
- Court found district court made three legal errors in irreparable harm analysis: (1) considering public harm instead of plaintiff-specific harm, (2) presuming irreparable harm from a CWA violation, (3) relying on expert testimony that only showed increased risk, not likelihood of harm.
- Chemours remains subject to an EPA administrative consent order addressing permit compliance, but the immediate threat of court-ordered production changes or temporary cessation is removed.
- Chemours had reported to the district court in July 2025 that EPA conditionally approved its PFAS abatement projects and that it had complied with permit limits since that time.
Before · The news · First close · A day later · A week later
Replay the market's reaction
Step through every 5 minutes around the news, then see how it compares with similar events.
Subscribe for Full Access