? NEUTRALIMPACT 5/10 6-K filed Apr 20, 2026 at 13:08 ET
B2Gold updated investors on a fire at its Goose Mine that damaged the crushing circuit, resulting in a temporary reduction in gold production for Q2 2026. The company expects to repair the circuit by Q3 2026 at an estimated cost of C$10 million and maintains full-year guidance, indicating the impact is contained to one quarter.
- Fire occurred on April 16, 2026, at the Goose Mine, localized to the crushing circuit with no injuries.
- No damage to the mill or power facility; repairs expected to be completed in Q3 2026.
- Gold production forecast for Q2 2026 revised down to 18,000–20,000 ounces from ~29,000 ounces, a reduction of ~10,000 ounces.
- Full-year 2026 production guidance for Goose Mine remains unchanged at 170,000–230,000 ounces.