BHP · BHP disclosed a $2.0 billion cost overrun on its Jansen Stage 2 potash…

BHP Group Ltd · 6-K filed Jun 18, 2026 at 10:13 ET

At the news

BEARISHIMPACT 7/10

6-K filed Jun 18, 2026 at 10:13 ET

BHP disclosed a $2.0 billion cost overrun on its Jansen Stage 2 potash project (investment estimate increased from $4.9B to $6.9B) and expects to recognize a ~$2.3B impairment charge on the Jansen asset base ahead of its FY2026 results. The project remains 16% complete with first production now guided to late FY2031. Group FY2027 capex guidance is maintained at ~$11B.

  • Jansen Stage 2 total investment estimate increased from US$4.9B to US$6.9B (including contingencies)
  • First production for Jansen Stage 2 delayed to late FY2031 (previously late FY2029 per 2023 approval)
  • BHP expects to recognize an impairment charge of approximately US$2.3B (before and after tax) on the Jansen project
  • Jansen Stage 2 is 16% complete with engineering at 83% complete as of end-May 2026